On a building project, money moves down a chain of contracts from owner to general contractor to subcontractors and suppliers. Construction contract management software earns its keep by holding that chain: who owes whom, under which clause, by which date, and what bond stands behind it. On federal work, statutes fix several of those dates.

What does construction contract management software need to track?

Construction contract management software needs to track each contract in the payment chain, the payment and notice terms in each, the bonds and their sureties, every payment application and withholding, and the waivers exchanged for each payment. A dispute on a project usually turns on one of those records, months after the work was done.

The general stages of a contract's life are covered in the overview of contract management software. Construction differs because one project produces dozens of linked contracts, and the rights of a supplier three tiers down can depend on what the prime contract says. A record that treats each subcontract as a separate document misses those links.

Project records such as daily logs, schedules, requests for information and change orders are a related subject, discussed in the post on AI for construction lawyers, including how notice provisions are read. This post stays with the payment chain.

Contract tierMain payment terms to recordSecurity behind payment
Owner and general contractorProgress payment schedule, retainage, final payment conditionsOn federal work, the government's own obligation
General contractor and subcontractorPayment timing, withholding rights, retainage, any pay-if-paid clauseThe prime's payment bond on federal work
Subcontractor and supplierPayment terms, notice requirementsThe prime's payment bond, if notice is given in time

Payment and performance bonds under the Miller Act

On federal construction, the Miller Act requires that before a contract over $100,000 is awarded for the construction, alteration or repair of a public building or public work, the contractor furnish a performance bond and a payment bond. The FAR applies the requirement to construction contracts exceeding $150,000.

The requirement is in 40 U.S.C. 3131. The performance bond protects the government, in an amount the contracting officer considers adequate. The payment bond protects all persons supplying labor and material in carrying out the work. Its amount equals the total amount payable under the contract unless the contracting officer determines in writing, with specific findings, that this is impractical and sets another amount, which may not be less than the performance bond.

The dollar figure in the statute is not the one contracting officers apply. FAR 28.102-1 says the bonds statute, formerly known as the Miller Act, requires performance and payment bonds for any construction contract exceeding $150,000. For construction contracts greater than $35,000 but not greater than $150,000, it requires the contracting officer to select two or more alternative payment protections, such as a payment bond, an irrevocable letter of credit or a tripartite escrow agreement. The record should hold whichever protection the contract actually required.

A contractor's records should hold both bonds, the surety's name and contact details, the bond amounts and any rider that changes them. A subcontractor or supplier that has not been paid may need a copy of the bond. Under 40 U.S.C. 3133(a), the contracting agency shall furnish a certified copy of the payment bond and the contract to a person who submits an affidavit that it supplied labor or material for the work and has not been paid, or that it is being sued on the bond. That copy is prima facie evidence of the contents, execution and delivery of the original.

The Miller Act covers federal work only. State public projects and private projects are governed by their own law and their own contracts, and the record should say which regime applies to each project.

Who can sue on a Miller Act payment bond, and by when?

A person who supplied labor or material and is unpaid 90 days after its last work may sue on the payment bond. A person with a contract only with a subcontractor must also give the prime contractor written notice within those 90 days. Every suit must be brought within one year of the last work.

Section 3133(b) sets out those rights in three parts, and construction contract management software should turn each into a date.

  1. First-tier claimants. A person that furnished labor or material under a contract for which a payment bond was furnished, and has not been paid in full within 90 days after the day it last performed labor or supplied material, may bring a civil action on the bond.
  2. Second-tier claimants. A person with a direct contract with a subcontractor, but no contract with the prime contractor, may sue only on giving written notice to the prime within 90 days from its last labor or material. The statute requires the amount claimed to be stated with substantial accuracy, together with the name of the party to whom the material was supplied or for whom the labor was done. The notice must be served by a method that provides written, third-party verification of delivery, or as a United States marshal may serve a summons.
  3. The suit itself. It is brought in the name of the United States for the use of the claimant, in the federal district court where the contract was to be performed, no later than one year after the claimant's last labor or material.

Everything turns on the date of last work. A record that holds only invoice dates will not answer the question. Delivery tickets, daily logs and the last day a crew was on site are the evidence, and they should be linked to the subcontract they belong to.

A hypothetical second-tier supplier on a federal project
  1. Day 0

    Supplier makes its last delivery to the subcontractor's site

  2. Day 60

    Invoice still unpaid; supplier's counsel reviews the bond

  3. Day 85

    Written notice to the prime, sent by tracked courier

  4. One year after day 0

    Last day to file suit on the payment bond

Waivers of bond rights and lien waivers

Waivers of payment rights are routine in construction, traded for each progress payment. The Miller Act limits waivers of the right to sue on a federal payment bond: such a waiver is void unless it is in writing, signed by the person whose right is waived, and executed after that person has furnished labor or material for the work.

That rule is in 40 U.S.C. 3133(c). Its effect on a record is simple to state. A waiver signed in the subcontract itself, before any work, does not waive a Miller Act bond right. A waiver signed after work began may, if it meets the three conditions. The date of execution, compared with the date work started, is the fact that matters.

On private projects, payment rights are often secured by liens on the property, and the parties exchange lien waivers. Lien rights and lien waivers are governed by state law, so the state statute is the source to read. The record should keep each waiver with the payment it was exchanged for, so that a conditional waiver can be matched to the check that made it effective.

Subcontract payment clauses under the federal Prompt Payment Act

The federal Prompt Payment Act requires every federal construction contract to make the prime contractor include, in each subcontract, a clause requiring payment for satisfactory performance within 7 days of the prime being paid by the agency, and an interest penalty clause for late payment. The same clauses must flow down to every lower tier.

The text is 31 U.S.C. 3905. Subsection (b) sets the 7-day payment clause and the interest penalty clause, with interest at the rate in section 3902(a). Subsection (c) requires the prime to make each subcontractor include conforming clauses in its own subcontracts, and so on down the chain.

Subsection (d) preserves room to negotiate. Parties may agree that the prime or a subcontractor retains a specified percentage of each progress payment without cause, which is retainage, and may agree on withholding for deficient performance. Withholding without a late payment penalty requires a written notice that, under subsection (g), specifies the amount withheld, the specific causes under the subcontract, and the remedial actions the subcontractor must take to be paid, with a copy of a prime contractor's notice to the government.

Subsection (e) then sets the steps after a withholding: reduce the progress payment by no more than the noticed amount, pay within 7 days after the deficiency is corrected, and notify the government of the amounts and the dates withholding began and ended. Each of those is a task with a date, and each belongs in construction contract management software beside the subcontract and the payment application it concerns.

Are pay-if-paid clauses enforceable?

A pay-if-paid clause makes the owner's payment to the general contractor a condition of the general contractor's duty to pay a subcontractor. Whether that is enforceable depends on state law. North Carolina's statute says payment by the owner is not a condition precedent to payment of a subcontractor, and an agreement to the contrary is unenforceable.

The North Carolina provision is G.S. 22C-2. It says performance by a subcontractor in accordance with its contract entitles it to payment from the party with whom it contracts. Payment by the owner to a contractor is not a condition precedent for payment to a subcontractor, and payment by a contractor to a subcontractor is not a condition precedent for payment to any other subcontractor.

This post does not survey other states. The governing state's law is the one to read. For contract records, the practical step is to tag each subcontract's payment-condition clause with its governing law and the project's location, so the question can be put to the right statute when a payment stalls.

Closing out a construction contract: retainage and final papers

Closeout is when retainage is released, final waivers are exchanged, warranties start and the last claims are asserted. Construction contract management software should hold a closeout list for every contract in the chain, because each item on it depends on a document from a different party.

On federal work, retainage is constrained in one more way. Under subsection (h) of 31 U.S.C. 3905, a prime contractor may not request payment from the agency of an amount withheld or retained under subsection (d) until it has determined and certified to the agency that the subcontractor is entitled to it. The record of that certification belongs with the subcontract.

  • Retainage held at each tier, and the condition for its release
  • Final waivers from each subcontractor and supplier, matched to final payments
  • Bond claim dates still open, counted from each claimant's last work
  • Warranty start dates, and who is responsible for each warranty
  • As-built documents and operation manuals delivered under the contract
  • Claims or disputes still pending, with their own deadlines

A construction project funded by a federal grant, rather than a direct federal contract, also brings grant rules into the subcontracts, discussed in the post on contract management software for nonprofits. When a payment dispute becomes a matter, the project file is large and mixed, and Lucerna Law's approach to files is described in the product section of the home page. This post describes what the statutes say. It is not advice about any project or claim.